Safety Analysis on the Volume Increase of Auxiliary Water Tank for Number One and Two Units of Fuqing Nuclear Power Plant |
TONG Lili1, SHAO Ge1, GU Jian2, XUE Junfeng2, PENG Jianping2, WANG Zhiqiang2 |
1. School of Mechanical Engineering, Shanghai Jiao Tong University, Shanghai 200240, China;2. CNNC Fujian Fuqing Nuclear Power Co., Ltd., Fuqing 350318, Fujian Province, China |
|
|
Abstract: When main feed water system or start-up feed water system is unavailable, auxiliary feed water system, as Engineered Safety Facility (ESF), provides water for Steam Generators (SG) to remove the stored and decay heat from the reactor core. In order to improve the safety of Nuclear Power Plants (NPPs) and increase operational flexibility, the water inventory of the auxiliary feed water tank is increased in the number one and two units of Fuqing NPP. The model of the NPP is built based on mechanical safety analytical code, and conservative assumptions are used in the calculation. Three typical accident sequences, such as loss of main feed water, loss of offsite power in category II accident, and main feed water line break in category IV, are selected to analyze whether or not the inventory in auxiliary water tank after improvement satisfies the relevant requirements in RCC-P. The results show that auxiliary water inventory of 713m3 is needed for loss of main feed water accident, auxiliary water inventory of 723m3 is needed for loss of offsite power accident, and auxiliary water inventory of 799m3 is needed for main feed water line break accident. The inventory in auxiliary water tank after improvement satisfies the requirements for category II and IV accidents. The safety of NPP is improved due to the inventory redundancy and a time window is also provided for the operators to perform related accident procedures.
|
Received: 24 December 2012
|
|
|
|
|
|
|
|